Sg Buloh Hospital already went live. Congrats to Sg Buloh team for going live without a problem. Hehehehe... Luckily the only problem did not caused by SP. Received report from ManTan, ITD in Level 3 'gelap gulita'. Hehehe. Radicare have to shut down the power due to water leakage during flush work for the main water tank. The incident happens just before the go live exercise lak tuh...

Besides than that, the exercise is running smoothly. No complaint on printing slow, system slow or network down. Good and kudos to all the team members involved on implementing all systems in Sg Buloh especially to my team NSU. Congrats also to you guys for making not only good but a great preparations to solve all problems before the go live exercise.